About the Rehabilitation of Section 28
Pipeline to Brattle Court Pumping Station Project
Massachusetts Water Resources Authority


MORE INFORMATION
map of project Section 28 - MWRA
Project Map - MWRA Section 28 Rehab, Arlington
Project Update

CONSTRUCTION UPDATE

GO TO ARCHIVE


CONTACT US
If you have questions or concerns about this project, please contact Jeffrey McLaughlin, MWRA Community Relations Manager, at (617) 660-7976.

Work on MWRA's project to rehabilitate the Section 28 pipeline in Arlington was complete in May, 2011.

The Section 28 project took place in 3 phases, including the cleaning and cement-mortar-lining of approximately 6,250 feet of 20-inch- diameter, cast-iron pipe. Section 28, which was constructed in 1899, provides suction to the Brattle Court Pump Station in Arlington. The project included landscaping restoration.

The Brattle Court Pump Station serves the Northern Extra High System, which includes Bedford, Lexington, and parts of Arlington, Belmont, Waltham, and Winchester. Section 28 is the oldest of the suction mains that serve the pump stations. The rehab of section 128, along with the future replacement of the Brattle Court Pump Station discharge main improved the suction and discharge capacity of the Brattle Court Pump Station.

J.D'amico Inc., of Randolph, Massachusetts was the MWRA contractor for this project. The project was awarded at a cost of $1.9 million.

PHASE 1 - COMPLETE

In Fall 2009, the contractor cleaned and relined approximately 6,000 feet of 20-inch cast iron pipeline from Brattle Street to Massachusetts Avenue.

PHASE 2 - COMPLETE

Work included:

  • Continued cleaning and relining
  • Removal of two valves and valve chambers that connect Section 28 to MWRA's WASM 3 line
  • Installation of new 20-inch ductile iron pipes and valves
  • New interconnections to a 12-inch water main owned by the Town of Arlington.

PHASE 3 - COMPLETE

Work took place at the eastbound lane of Massachusetts Avenue east of Pleasant Street and on the sidewalk adjacent to area businesses. This phase included:

  • Installation of a new 54-inch valve on MWRA's WASM 3 line
  • New interconnections with Section 28

Back to top

Updated July 5, 2011