06/02/13 - Night Work:
MWRA's contractor begins night work (8PM-6AM) on Sunday, June 2nd at the intersection of River and Willow Streets in Waltham. D’Amico, Inc. is excavating one of eleven access pits at this location for the purpose of placing a new 24” inch water main into an existing 30” pipe.
Night work is limited to two locations in Waltham: The intersection of Willow Street and River Street and the intersection of River Street and Seyon Street. Both intersections are very busy during the day, therefore night work is required by the City of Waltham. Night work in each location will take three weeks. |
05/16/13 - Traffic Detours, May 20 - 24, 2013
As the contractor moves down the road, local traffic will be diverted. Detours will change approximately once a week. The first detour will begin Monday, May 20 and has been approved by the City of Waltham Police Department through Friday, May 24. |