Update for MWRA Reading Extension Sewer Rehabitation
(MWRA Contract 7164)

propoed project work area

Proposed project plan and location

Go to Project Updates

About this Project:

This project is in design and will take place in Reading. Planned work will include the rehabilitation of 13,100 feet of sewer pipe and 62 manholes and structures with cured-in-place lining. It also includes bypass pumping and flow diversion and coordination with MWRA's Northern Intermediate High, Eversouce Energy and Rail Trail Projects.

For more information, please contact Jeff McLaughlin at (617) 305-5762, or by email at Jeffrey.McLaughlin@mwra.com.

Project Updates

January 9, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Progress Photos

Wet out - impregnation of resin

Wet-out: impregnation of resin

lateral service lining

Lateral service lining

lining wrapped around device

Lining wrapped around device

November 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Upcoming Work

  • RETV pipelines
  • Repair defective CIPP
  • Followed by manhole rehab
  • CIPPL install complete

Manhole rehabilitation

CIPP spot repair

October 2, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Upcoming Work

  • RETV pipelines repairs
  • Manhole rehab

Special repair - drilling access holes

Manhole frame and cover replacement

September 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Upcoming Work

  • RETV pipelines repairs
  • Manhole rehab
  • CIPPL install completed

Progress Photos

progress photo 1
progress photo 2

June 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Upcoming Work

Approximately 4,000 linear feet of CIP inversions remain, followed by manhole rehabilitation


Progress Photo

CIPP inversion at cemetery

CIPP inversion at cemetery

May 4, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Progress Photos

Progress photo

Sewer preliner

Curing liner in place

Updates will be posted in this section. Sign up for electronic project updates through our Everbridge notifications service.

 