Return to mwra.com home

Massachusetts Water Resources Authority
PROJECT UPDATE

Date:

Updated February 27, 2020

Contact:

Jeffrey McLaughlin
(617) 305-5762, Jeffrey.McLaughlin@mwra.com


Update for MWRA Alewife Brook Pump Station
Rehabilitation Project
(MWRA Contract 6797)

MWRA's Alewife Brook Pump Station in Somerville was constructed in 1951
and serves portions of Arlington, Belmont, Cambridge, Medford and Somerville.

MWRA CCR Cover

About this Project:

The Alewife Brook Pump Station Rehabilitation Project (MWRA Contract 6797) will improve the operating capacity and reliability of a sewer station that pumps wastewater flows from Arlington, Belmont, Cambridge, Medford and Somerville through the North Metropolitan and North Metropolitan Relief Sewers toward the Deer Island Treatment Plant.

A First in Climate Change Resilience:

The rehabilitation of the Alewife Brook Pump Station is the first MWRA project to incorporate new measures to protect equipment and facilities from the affects of potential climate change. This project is important step in MWRA's long-term efforts to protect the sewer system's overall ability to operate during wet weather events and to recover from them.

The Alewife Brook Sewer Rehabilitation Project will provide flood
protection for a potential 2.5-foot surge above the 100-year flood elevation.

Work in Somerville:

Under MWRA Contract 6797, MWRA's contractor, Barletta Engineering Corporation, will make major operational and structural improvements to the Alewife Brook Pump Station.

Existing sewer pumps, original to the 1951 station, no longer operate with as-designed efficiency. They will be replaced by two, higher-capacity wet-weather pumps and a dry-weather pump, with a third wet-weather pump available for standby use.

Other operational improvements include the replacement of motors, gear drives, controls, screens, sluice gates and generators.

The Alewife Brook Pump station's HVAC systems, paint, roofing and insulation will also be updated and new flow meter will be installed on the Alewife Brook Conduit.

MWRA Contact:

If you have any questions please email Jeff McLaughlin or call (617) 305-5762.

To receive electronic project updates, please register your email address with the MWRA Alerts Service, provided through Everbridge.

Updates

February 27, 2020

Sign up for electronic project notifications and updates through our Everbridge service.

Work Update: Project near completion.

Upcoming Work: Paving to resume in the spring.

November 4, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Stripped all asphault off driveway
  • Pavement being installed
project photo

Stripping asphalt

project photo

Pavement being installed

October 9, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Paving is about to begin.

September 12, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Pump test to be scheduled.
project photo

Installation of additional supports at generator exhaust

August 7, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Photos:

construction photo

MWRA intern tour of facility

July 8, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Work Progress:

Vibration meeting scheduled for July.

Construction Photos:

construction photo

Casting in place and cover for inlet chamber

June 4, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Photos:

project photo
project photo

Hydroseeding entire site

project photo
project photo

Grass beginning to grow on site

May 3, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Obtained Temporary Occupancy Permit
  • Tested 66-inch Flow Meter
  • BEC Conducted Additional Vibration Tests
  • MWRA Conducted Vibration Tests
  • Installed Conduit and Ductbank from Meter
  • Installed Bollard in front of Gas Meter
  • Began Site Restoration
  • Partially Removed Construction Fencing
  • Installed Back Flow Prevention in Existing Piping

Progress Photos:

Installation of bollards in front of gas meter

Installation of loam for site restoration

 

April 8, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Formed, installed rebar, and placed concrete for roof of metering vault
  • Pulled wire for flow meter in metering vault
  • Completed staff training
  • Completed demolition of bypass pumping system and removed piping pumps from the site

Progress Photos:

Roof on Meter Vault

progress image 1
progress image 2
progress image 3

Driveway leak

progress image 4

March 11, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Boiler place in service
  • Direct Digital Control (DDC) for HVAC programmed
  • Completed PCB punch list items
  • Installed and tested spool piece
  • Formed, installed rebar and placed concrete for support of spool piece
  • Began demolition of bypass pumping system
  • Began training
project photo

Spool piece bypass removal

project photo

Connecting concrete pipes

project photo

Dismantling of the bypass

project photo

SCADA training

January 30, 2019

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Continued to Address HVAC system
  • Conducted Vibration Testing on December 21, 2018
  • Completed Loop Check Outs on SCADA
  • Continued Painting
  • Installed Encapsulation System on Pump and Screen Floors

Upcoming Work:

  • Complete HVAC Work
  • Complete PCB Abatement
  • Testing
  • Training 
  • Remove Bypass
  • Repair ABC Conduit
  • Install Spare Conduit from Transformer to Pole

December 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Construction Update:

  • Completed fire alarm testing
  • Completed wiring security
  • Completed pump performance testing
  • Completed wiring gas monitoring control panel
  • Continued loop testing instrumentation and equipment
progress photo

MCC pump test, running at about 50% speed

progress photo

Drone photograph - overview of site

progress photo

Drone photograph - asphalt shingle roof and membrane roof

Upcoming work:

  • Complete electrical work
  • Complete HVAC work
  • Complete painting/PCB abatement
  • Complete SCADA
  • Finish wet checkout
  • Functional testing
  • Final testing

November 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Work update:

  • Began wiring security system
  • Began wiring gas monitoring control panel
  • Began loop testing instrumentation and equipment
  • Installed railings at stairs in screen room.
  • Finished wiring pumps
  • Completed dry check out of equipment
  • Completed wet check out of pumps
  • Wired standby generator
pump room

Finished painting in pump room

valves

Checking valve functioning

fire alarm

Work on fire alarm

scada

Wiring in Scada control panel

knife valve

Opening knife gate valve

pump testing

Pump testing

October 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Work update:

  • Continued to operate bypass system
  • Completed installation of wire
  • Began terminating wires at equipment and control panels
  • Continued installation of HVAC equipment
  • Continued painting
  • Began installation of Louvers
  • Began Dry Check out of equipment (pumps and grinders complete)
  • Continued mounting instrumentation and control panels

Upcoming work:

  • Complete electrical work
  • Complete HVAC work
  • Complete plumbing work
  • Finish Dry Checkout
  • Perform Wet Checkout
  • Functional Testing

Louver in front of new generator

Level transmitters along new masonry wall

Screen and grinder control panels

Cable tray and cables in generator room

Raceway and wires

Pump cable terminations

Painting second coat on wall in pump room

Exhaust fan in screen room and HVAC work

September 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Work update:

  • Installed 3 new wet weather pumps
  • Installed discharge piping and valves
  • Installed 2 new grinder units downstream of screens
  • Completed replacement of roof
  • Continued installation of conduit and wire
  • Continued installation of HVAC equipment
  • Continued installation of new plumbing piping
  • Began installation of instrumentation
  • Replaced all windows and doors
New wet weather pumps and discharge piping and valves

New wet weather pumps and discharge piping and valves

Conduit being installed in screen room

Conduit being installed in screen room

Traveling screen with downstream grinder unit

Traveling screen with downstream grinder unit

June 1, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Work update:

  • Began Installation of Supports for Grating
  • Installed Switch Gear/VFDs on Grating Supports
  • Installed Air Handling Unit
  • Cut Opening in Wall Between Screen Room and Operating Room
  • Installed Structural Supports for Opening
structural support

Installation of structural support for grating and equipment

switchgear

Installation of switchgear for new pumps

ceiling tiles

Installation of ceiling tiles in screen room

hand operated gates

Installation of hand operated gates in the screen channels

hvac duct work

Insulated HVAC duct work

electrical raceways

Electrical raceways in operating room

MWRA asbestos removal

Start of asbestos removal

MWRA asbestos removal

Asbestos removal

MWRA asbestos removal

Asbestos removal

May 3, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Work update:

  • Completed installation of fire rated plywood base for ceiling tiles in operating room and screen room
  • Installed ceiling tiles in operating room
  • Began installation of duct bank behind the pump station
  • Began installation of ductwork and electrical raceways in the operating room
  • Began installation of heating return and supply lines
  • Painted beams in screen room and operating room
  • Painted crane in screen room.

Upcoming work:

  • Finish installation of ceiling in screen room
  • Continue rough piping for electrical work
  • Continue installation of HVAC equipment
  • Complete installation of hand operated sluice gates
  • Installation of interior water and gas piping
  • Asbestos abatement at roof
  • Begin installation of new roof and wastewater pumps
progress image

Operating room before ceiling tile installation

progress image

Operating room with cling tiles installed

progress image

Electrical conduits

progress image

Pouring concrete slabs for equipment

April 20, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Work update:

  • Continued to operate bypass system
  • Primed ceilings, beams and walls
  • Installed framing for ceiling tiles
  • Applied spray foam insulation to the ceiling
  • Began installation of plywood base for ceiling tiles
  • Placed grout in stop log grooves for sluice gate installation
  • Removed generator from generator room.

Upcoming work:

  • Finish Installation of ceiling on operating level and in screen room
  • Apply first coat of finish paint to beams on operating level and in screen room
  • Begin installation of sluice gates
  • Take delivery of new generator
  • Miscellaneous electrical work
  • Placed grout in stop log grooves for sluice gate installation
  • Miscellaneous HVAC work.
Project image workers
project image ceiling
project image ceiling

Ceiling Installation

March 6, 2018

Sign up for electronic project notifications and updates through our Everbridge service.

Completed work to date:

  • Continued to operate bypass system
  • Completed PCB abatement of Screen Room
  • Completed PCB Abatement of Upper Pump Room
  • Modified concrete floor to allow for installation of new screens
  • Began installation of the new screens.
  • Completed transfer of power to temporary power source.

Upcoming work:

  • Finish installing screens
  • Prime ceiling in screen room
  • Prime Beams in screen room
  • Begin installation of ceiling framing
  • Begin installation of sluice gates
  • Miscellaneous electrical work

Construction Photos:

MWRA PCB abatement

PCB abatement

MWRA Screen installation
MWRA Screen installation

Screen installation

For more information, please contact Jeff McLaughlin at (617) 305-5762.

02/14/18

Sign up for electronic project notifications and updates through our Everbridge service.

Completed work to date:

  • Completed Installation of Bypass System
  • Tested Bypass System
  • Bypass Pump System placed in service January 2, 2018
  • 2 storms since bypass went into service (January 12/13 and January 23)
  • Completed PCB Abatement of Lower Level
  • Completed PCB abatement of Generator Room
  • Began PCB abatement of Screen Ro
  • Performed routine maintenance on bypass pump system
  • Completed demolition of screens
  • Began demolition of pumps and piping
  • Began demolition of electrical and scada equipment
  • Completed gas service installation to building

Upcoming work:

  • Complete PCB removal
  • Continue demolition of mechanical and electrical equipment
  • Transfer necessary lighting and heating to temporary power source
  • Continue operation and maintenance of bypass pumping system

Construction Photos:

progress photo
progress photo
progress photo
progress photo
progress photo

For more information, please contact Jeff McLaughlin at (617) 305-5762.

10/13/17

Construction Photos

Sign up for electronic project notifications and updates through our Everbridge service.

abatement

New haybales at Alewife

electrical

Re-assembly of piping

For more information, please contact Jeff McLaughlin at (617) 305-5762.

July, 2017

Construction Photos

Sign up for electronic project notifications and updates through our Everbridge service.

abatement

PCB abatement

electrical

Delivery of electrical components to site

demolition

Demolition of the boiler room

For more information, please contact Jeff McLaughlin at (617) 305-5762.

June 12, 2017

Construction Update

 Work accomplished: June 2017

  • Installed temporary sewerage bypass pumps and piping around perimeter of facility

  • Working on removal of PCB paint inside facility

Future Work:

  • Continue PCB Abatement inside facility

  • Installation of new gas line across Alewife Brook Parkway

Aerial shot of sewerage bypass system

Aerial shot of sewerage bypass system

Sign up for electronic project notifications and updates through our Everbridge service.

If you have any questions please email Jeff McLaughlin or call (617) 305-5762.

March 10, 2017

In order to complete new exterior and interior renovations to the Alewife Brook Pumping Station, it is necessary to ‘by-pass’ the pump station for a period of a year. This is accomplished with pumps and piping outside the building to reroute flows while maintaining normal pumping and flow capacity for the residents of Somerville, Cambridge and Arlington.

Design, preparation and contingency planning for this process are complete and mobilization of the pumps and installation of the ‘by-pass’ has begun. It is currently anticipated that the bypass system will be operation by the end of March 2017.

August 16, 2017

Work began in August, 2016.

If you have any questions please email Jeff McLaughlin or call (617) 305-5762.


Follow us

twitter icon
flickr
YouTube button
Sign Up for Everbridge Notifications from MWRA