Updates
February 27, 2020
Sign up for electronic project notifications and updates through our Everbridge service.
Work Update: Project near completion.
Upcoming Work: Paving to resume in the spring.
November 4, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Stripped all asphault off driveway
- Pavement being installed
October 9, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Paving is about to begin.
September 12, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Pump test to be scheduled.
Installation of additional supports at generator exhaust
August 7, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Photos:
MWRA intern tour of facility
July 8, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Work Progress:
Vibration meeting scheduled for July.
Construction Photos:
Casting in place and cover for inlet chamber
June 4, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Photos:
Grass beginning to grow on site
May 3, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Obtained Temporary Occupancy Permit
- Tested 66-inch Flow Meter
- BEC Conducted Additional Vibration Tests
- MWRA Conducted Vibration Tests
- Installed Conduit and Ductbank from Meter
- Installed Bollard in front of Gas Meter
- Began Site Restoration
- Partially Removed Construction Fencing
- Installed Back Flow Prevention in Existing Piping
Progress Photos:
Installation of bollards in front of gas meter
Installation of loam for site restoration
April 8, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Formed, installed rebar, and placed concrete for roof of metering vault
- Pulled wire for flow meter in metering vault
- Completed staff training
- Completed demolition of bypass pumping system and removed piping pumps from the site
Progress Photos:
March 11, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Boiler place in service
- Direct Digital Control (DDC) for HVAC programmed
- Completed PCB punch list items
- Installed and tested spool piece
- Formed, installed rebar and placed concrete for support of spool piece
- Began demolition of bypass pumping system
- Began training
Spool piece bypass removal
Connecting concrete pipes
Dismantling of the bypass
January 30, 2019
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Continued to Address HVAC system
- Conducted Vibration Testing on December 21, 2018
- Completed Loop Check Outs on SCADA
- Continued Painting
- Installed Encapsulation System on Pump and Screen Floors
Upcoming Work:
- Complete HVAC Work
- Complete PCB Abatement
- Testing
- Training
- Remove Bypass
- Repair ABC Conduit
- Install Spare Conduit from Transformer to Pole
December 1, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Construction Update:
- Completed fire alarm testing
- Completed wiring security
- Completed pump performance testing
- Completed wiring gas monitoring control panel
- Continued loop testing instrumentation and equipment
MCC pump test, running at about 50% speed
Drone photograph - overview of site
Drone photograph - asphalt shingle roof and membrane roof
Upcoming work:
- Complete electrical work
- Complete HVAC work
- Complete painting/PCB abatement
- Complete SCADA
- Finish wet checkout
- Functional testing
- Final testing
November 1, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Work update:
- Began wiring security system
- Began wiring gas monitoring control panel
- Began loop testing instrumentation and equipment
- Installed railings at stairs in screen room.
- Finished wiring pumps
- Completed dry check out of equipment
- Completed wet check out of pumps
- Wired standby generator
Finished painting in pump room
Checking valve functioning
Wiring in Scada control panel
October 1, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Work update:
- Continued to operate bypass system
- Completed installation of wire
- Began terminating wires at equipment and control panels
- Continued installation of HVAC equipment
- Continued painting
- Began installation of Louvers
- Began Dry Check out of equipment (pumps and grinders complete)
- Continued mounting instrumentation and control panels
Upcoming work:
- Complete electrical work
- Complete HVAC work
- Complete plumbing work
- Finish Dry Checkout
- Perform Wet Checkout
- Functional Testing
Louver in front of new generator
Level transmitters along new masonry wall
Screen and grinder control panels
Cable tray and cables in generator room
Painting second coat on wall in pump room
Exhaust fan in screen room and HVAC work
September 1, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Work update:
- Installed 3 new wet weather pumps
- Installed discharge piping and valves
- Installed 2 new grinder units downstream of screens
- Completed replacement of roof
- Continued installation of conduit and wire
- Continued installation of HVAC equipment
- Continued installation of new plumbing piping
- Began installation of instrumentation
- Replaced all windows and doors
New wet weather pumps and discharge piping and valves
Conduit being installed in screen room
Traveling screen with downstream grinder unit
June 1, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Work update:
- Began Installation of Supports for Grating
- Installed Switch Gear/VFDs on Grating Supports
- Installed Air Handling Unit
- Cut Opening in Wall Between Screen Room and Operating Room
- Installed Structural Supports for Opening
Installation of structural support for grating and equipment
Installation of switchgear for new pumps
Installation of ceiling tiles in screen room
Installation of hand operated gates in the screen channels
Electrical raceways in operating room
Start of asbestos removal
May 3, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Work update:
- Completed installation of fire rated plywood base for ceiling tiles in operating room and screen room
- Installed ceiling tiles in operating room
- Began installation of duct bank behind the pump station
- Began installation of ductwork and electrical raceways in the operating room
- Began installation of heating return and supply lines
- Painted beams in screen room and operating room
- Painted crane in screen room.
Upcoming work:
- Finish installation of ceiling in screen room
- Continue rough piping for electrical work
- Continue installation of HVAC equipment
- Complete installation of hand operated sluice gates
- Installation of interior water and gas piping
- Asbestos abatement at roof
- Begin installation of new roof and wastewater pumps
Operating room before ceiling tile installation
Operating room with cling tiles installed
Pouring concrete slabs for equipment
April 20, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Work update:
- Continued to operate bypass system
- Primed ceilings, beams and walls
- Installed framing for ceiling tiles
- Applied spray foam insulation to the ceiling
- Began installation of plywood base for ceiling tiles
- Placed grout in stop log grooves for sluice gate installation
- Removed generator from generator room.
Upcoming work:
- Finish Installation of ceiling on operating level and in screen room
- Apply first coat of finish paint to beams on operating level and in screen room
- Begin installation of sluice gates
- Take delivery of new generator
- Miscellaneous electrical work
- Placed grout in stop log grooves for sluice gate installation
- Miscellaneous HVAC work.
March 6, 2018
Sign up for electronic project notifications and updates through our Everbridge service.
Completed work to date:
- Continued to operate bypass system
- Completed PCB abatement of Screen Room
- Completed PCB Abatement of Upper Pump Room
- Modified concrete floor to allow for installation of new screens
- Began installation of the new screens.
- Completed transfer of power to temporary power source.
Upcoming work:
- Finish installing screens
- Prime ceiling in screen room
- Prime Beams in screen room
- Begin installation of ceiling framing
- Begin installation of sluice gates
- Miscellaneous electrical work
Construction Photos:
PCB abatement
Screen installation
For more information, please contact Jeff McLaughlin at (617) 305-5762.
02/14/18
Sign up for electronic project notifications and updates through our Everbridge service.
Completed work to date:
- Completed Installation of Bypass System
- Tested Bypass System
- Bypass Pump System placed in service January 2, 2018
- 2 storms since bypass went into service (January 12/13 and January 23)
- Completed PCB Abatement of Lower Level
- Completed PCB abatement of Generator Room
- Began PCB abatement of Screen Ro
- Performed routine maintenance on bypass pump system
- Completed demolition of screens
- Began demolition of pumps and piping
- Began demolition of electrical and scada equipment
- Completed gas service installation to building
Upcoming work:
- Complete PCB removal
- Continue demolition of mechanical and electrical equipment
- Transfer necessary lighting and heating to temporary power source
- Continue operation and maintenance of bypass pumping system
Construction Photos:
For more information, please contact Jeff McLaughlin at (617) 305-5762.
10/13/17
Construction Photos
Sign up for electronic project notifications and updates through our Everbridge service.
For more information, please contact Jeff McLaughlin at (617) 305-5762.
July, 2017
Construction Photos
Sign up for electronic project notifications and updates through our Everbridge service.
Delivery of electrical components to site
Demolition of the boiler room
For more information, please contact Jeff McLaughlin at (617) 305-5762.
June 12, 2017
Construction Update
Work accomplished: June 2017
-
Installed temporary sewerage bypass pumps and piping around perimeter of facility
-
Working on removal of PCB paint inside facility
Future Work:
-
Continue PCB Abatement inside facility
-
Installation of new gas line across Alewife Brook Parkway
Aerial shot of sewerage bypass system
Sign up for electronic project notifications and updates through our Everbridge service.
If you have any questions please email Jeff McLaughlin or call (617) 305-5762.
March 10, 2017
In order to complete new exterior and interior renovations to the Alewife Brook Pumping Station, it is necessary to ‘by-pass’ the pump station for a period of a year. This is accomplished with pumps and piping outside the building to reroute flows while maintaining normal pumping and flow capacity for the residents of Somerville, Cambridge and Arlington.
Design, preparation and contingency planning for this process are complete and mobilization of the pumps and installation of the ‘by-pass’ has begun. It is currently anticipated that the bypass system will be operation by the end of March 2017.
August 16, 2017
Work began in August, 2016.
If you have any questions please email Jeff McLaughlin or call (617) 305-5762.