March 2, 2023
Sign up for electronic project notifications andupdates through our Everbridge service.
Upcoming Work:
- Substantial completion anticipated by end of February
- Site restoration to be completed Spring 2023
Reinstalled Granite Stair Treads
Stair Capstone Installation
Stairway Railing and New Door
Re-Installed Fencing Along Patio
Finished Topping Slab at Patio
North/East Side of Bastion
February 2, 2023
Sign up for electronic project notifications andupdates through our Everbridge service.
Upcoming Work:
- Complete Electrical Work
- Heat trace on Roof Drains
- Complete Lighting
- Insulate Roof Drains
- Repair patio
- Install new door
- Install railing
- Install windows
Reinstalled Granite Blocks at Stairs
East and North Side Granite Re-Installation complete on walls
Waterproofing at stairway
Metal flashing at Interface of roof and granite block
Installation of First Granite Stair Tread
Repointing of granite blocks on South side
December 28, 2022
Sign up for electronic project notifications andupdates through our Everbridge service.
Upcoming Work:
- Install Waterproofing on Roof
- Place second topping slab on Roof
- Replace parapet blocks
- Perform crack repair on interior of building
- Repair Patio
- Install new door
- Install railing
Reinstalled Granite Blocks
Placed Archstone over doorway
Bastion building from Archway bridge
Interior north wall concrete
Interior of building beams, roof planks and drain
Formed installed rebar and placed concrete for stairs
Formed, installed rebar and placed concrete for stairs
Rebar at the top of the landing
Partial placement on concrete stairs and heating blankets to keep everything warm
Hardened concrete on bottom of stairway and formed the rest going up
November 7, 2022
Sign up for electronic project notifications andupdates through our Everbridge service.
Upcoming Work:
- Place topping slab on roof planks
- Begin replacement of granite blocks
- Re-energize 13.8 KV cable (scheduled for 11/7/22)
- Install waterproofing on roof
North Wall rebar installation complete
Pumper truck for North Wall replacement
August 9, 2022
Sign up for electronic project notifications andupdates through our Everbridge service.
Upcoming Work:
- Removal of roof planks and beams
- Removal, labeling and storage of Parapet blocks
- Begin demolition of concrete walls
Floor installation and building supports
Removal of granite capstone at Stairwell
Removal of Roof and Abestos Mastic (bagged to keep the asbestos from spreading)
High winds caused scaffolding to fall apart but will be repaired
June 29, 2022
Work Completed:
- Installed structural monitoring points
- Removed windows and frames
- Built enclosure around electrical equipment to remain
- Installed engineer’s field trailer
- Continued work on roadway improvements
- Installed temporary fencing around project
- Submitted demolition plan
- Submitted electrical demolition plan
- Shut down power to 13.8KV cable
Upcoming Work:
- Injection grouting of wall cracks
- Injection grouting of wall cracks
- Install doka dance floor
- Install interior wall shoring
- Install support for cable tray
- Begin removal of roofing topping slab
Installed floats for external scaffolding
Building work platform for external scaffolding
Installation of turbidity curtain
April 28, 2022
Project updates will be posted throughout the period of construction.